case study · 6 min read

A Norwood 1924 stone-rubble basement: when sealing is most of the job

By Sam Reynolds, Greater Cincinnati radon specialist: the geology that makes this region Zone 1, the ANSI/AARST standards a correct install follows, and what actually gets a house under 2.0 pCi/L.. Published June 6, 2026.

A 1924 Sears-kit foursquare in Norwood tested at 13.6 pCi/L with hundreds of unsealed mortar joints between limestone-rubble blocks. The fix took two days and the sealing portion ran 60% of the labor. Here is how the mitigator approached it.

Need a radon mitigation quote in Greater Cincinnati? Talk to us now.

Call (513) 960-3089

The starting point

A 1924 Sears Modern Home foursquare in Norwood, 1,950 sqft of original construction, original limestone-rubble basement walls (mortar joints between irregular stone, no poured concrete on the perimeter), original earth-and-concrete-cap floor in the unfinished portion of the basement, partially-finished family room added in 1972 with a 4-inch concrete slab over the original floor.

The new owners had bought the home eight months earlier as a renovation project. Their contractor included radon testing in the pre-renovation due diligence: the 48-hour test came back at 13.6 pCi/L, more than three times the EPA action level. The contractor referred them to our dispatch line.

Why pre-1950 Norwood housing tests this high

The Cincinnati Arch geology runs uranium-bearing limestone and shale at relatively shallow depth across most of Norwood, Hyde Park, and Walnut Hills. Pre-1950 builders used local stone for foundations because it was cheap and abundant. The result is residential basements built directly into uranium-rich soil with hundreds of mortar-joint paths for soil gas to enter.

Norwood specifically has the highest documented pre-mitigation pCi/L averages in Hamilton County. Local mitigators have records of pre-mitigation readings above 30 pCi/L on a meaningful number of pre-1940 stone-basement homes. The 13.6 pCi/L on this 1924 foursquare is on the high end of typical for Norwood, not unusual.

The on-site assessment

The Cincinnati-area mitigator walked the basement for about an hour. Findings:

1. Hundreds of mortar joints in the limestone-rubble walls, most showing visible weathering and gaps where mortar had spalled. Rough estimate: 300-500 linear feet of joint length needing some level of sealing 2. Original earth-and-concrete-cap floor in the unfinished portion, with the cap broken in several places and partial dirt exposure 3. 1972 concrete slab in the finished portion, hairline-cracked but generally sealed 4. Original sump pit in the southwest corner with no liner, an unsealed lid, and a bypass float that had failed at some point in the past 5. Furnace and gas water heater in the basement, both natural-draft, both 12-15 years old (replaced from the 1924 originals at some point)

The mitigation strategy that emerged: active sub-slab depressurization on the 1972 slab portion, sub-membrane depressurization on the unfinished portion, aggressive mortar-joint sealing of the perimeter walls, sealed sump-pit lid integrated into the suction network. Single fan, two routing paths joining at the basement ceiling.

The quote

$3,840 fixed, broken out:

  • Slab core-drill suction pit + lid for the 1972 slab portion: $400
  • Sub-membrane suction pipe + reinforced 12-mil polyethylene barrier across the unfinished-floor portion: $850
  • Mortar-joint sealing across the entire perimeter wall: $1,400 (about 35% of total quote)
  • Sealed sump-pit lid + suction integration: $300
  • Stack routing through closet chase to attic to roofline: $350
  • Radonaway RP145 fan in attic enclosure + manometer + dedicated circuit: $400
  • Combustion-safety pre/post test on furnace and water heater: $140

The sealing line item dwarfed every other component. That is normal for Norwood pre-1950 stone-basement work; in some cases sealing reaches 50% of total labor.

Install (two days)

Day 1 (sealing-heavy): Crew of two on site 7:30 AM through 5:30 PM. Pre-install combustion-safety test on the furnace and water heater (both passed at acceptable margins). Mortar-joint sealing started at 9:00. The technique: clean each joint with a wire brush to remove loose material, apply a primer where the existing mortar was friable, then run polyurethane caulk into the joint and tool it flush. About 8 hours of joint-by-joint work. The two-person crew finished roughly 80% of the perimeter on Day 1.

Day 2 (mitigation install): Same crew 7:30 AM through 4:00 PM. Finish the remaining 20% of mortar-joint sealing in the morning. Slab core-drill done by 11:00. Sub-membrane barrier installed by 1:30. Stack routed through the closet chase, fan mounted in the attic enclosure, manometer placed and labeled by 3:30. Post-install combustion-safety test confirmed both natural-draft appliances still drafted properly. Power up and walk-through with the homeowner at 4:00.

End-of-Day-2 manometer reading: 1.1 inches water column negative pressure on the slab side, 0.7 on the sub-membrane side. Healthy.

The 48-hour retest

Continuous radon monitor placed in the 1972 finished family room (the same spot the original 48-hour test had been placed). 48-hour result:

1.6 pCi/L average. Down 88% from the 13.6 pCi/L pre-mitigation reading. Below the EPA-recommended 2.0 pCi/L post-mitigation target.

The key word in that delta: 88%. Norwood pre-1950 mitigations typically hit 80-90% reduction even from very high starting levels, but only when the sealing portion of the work is done properly. Cutting the sealing scope can leave a home at 4-6 pCi/L post-install: technically a passing reading on average but unstable, with seasonal swings back into action-level territory.

What the homeowner paid

Total: $3,840. About 1.6x the typical Cincinnati basement install ($2,400 high end), reflecting the extensive sealing scope. Most of that incremental cost is labor; materials for sealing are $200-$300 of the quote.

Annual electricity for the fan: about $90.

Why this case matters for other Norwood and pre-1950 homeowners

If you have a stone-rubble basement (Hyde Park, Norwood, Mt. Lookout, Walnut Hills, parts of Mariemont, parts of older Mason), expect a quote that allocates significant labor to mortar-joint sealing. If a contractor quotes a typical $1,200-$2,400 install on a pre-1950 stone-basement home without acknowledging the sealing scope, the install will likely under-perform.

Things to watch for in the on-site assessment: - Did the mitigator actually walk the perimeter and count linear feet of joint? - Is sealing called out as a separate line item, or buried in "miscellaneous"? - What polyurethane caulk product is being specified? (Sika 1A or DAP Polyurethane are the typical Cincinnati-area choices; cheaper acrylic-latex caulks fail within 2-3 years) - How many crew-hours are budgeted for sealing? (Should be 8-16 hours for typical Norwood-class work)

A credentialed NRPP mitigator who has done 30+ Norwood or Hyde Park stone-basement installs will give you those numbers without hesitation. A contractor who treats sealing as an afterthought is the wrong contractor for this kind of home.

Authoritative sources

  • US EPA

    Cincinnati and surrounding counties sit in EPA Radon Zone 1, the highest-risk classification.

  • EPA Citizen's Guide to Radon

    EPA recommends mitigation above 4.0 pCi/L and consideration of mitigation between 2.0 and 4.0 pCi/L.

  • Ohio Department of Health

    Ohio Radon Program guidance on testing, mitigation, and contractor licensure.

Ready to get started in Cincinnati?

Radon mitigation across Greater Cincinnati and Northern Kentucky since 2019, with every install performed by an NRPP-credentialed local mitigator. Mon-Sat 8am-7pm.

Call (513) 960-3089

Prefer to text? Open your texting app